Cedro Canal

Detailed Information

Supervision for the Design and Construction of the desander and complementary works for the adaptation of the Cedro Canal, section between Carrera 7 and Carrera 9 with Calle 153, Usaquén district, Cedro Golf neighborhood.

The activities carried out in the project consisted of the preparation of studies and designs for the construction of a desander, the construction of pre-excavated screens for the stabilization of the slopes of the adjacent roads, construction of a desander in the channel of the El Cedro canal, the reconstruction of the existing desander and the reconstruction of the concrete plates of the canal lining, which were in poor condition.

The access ramp to the sand trap was also built in 4,000 psi concrete with a thickness of 25 cm and the operating platform in MR-45 concrete (5,000 psi) with a thickness of 25 cm.

Datos Generales
Sector Hydraulic Infrastructure
Servicio Design and Construction Supervision
Fechas Inicio: 2012-10-01 | Fin: 2013-12-31
Estado Concluído
Localización Cundinamarca, Colombia
Cliente Empresa de Acueducto y Alcantarillado de Bogotá , EAAB